What Is a Manufacturing ERP? From BOM to Planning and Output Recording
A manufacturing ERP step by step: bill of materials, shortage calculation, order analysis, machine planning and scrap recording, with an evaluation checklist.
When a small or mid-sized factory says "we want a manufacturing ERP", it rarely means accounting software with a few extra columns. It means a system that builds an unbroken chain from receiving an order to recording production on a machine: what materials the order needs, what is in stock, what is short, and which machine and shift will make it. This article walks through a manufacturing ERP step by step and ends with a checklist for evaluating software.
How does a manufacturing ERP differ from a general ERP?
A general ERP covers purchasing, sales, warehouse and accounting. A manufacturing ERP has all of those and adds:
- A bill of materials (BOM): what each product is made of.
- Material shortage calculation: for a given run, how much of each component is needed and how much is short.
- Production planning: what is made on which machine, in which shift and by whom.
- Output recording: how much good output, scrap and rework was produced.
All four must connect to the warehouse and accounting, otherwise separate Excel files return.
Step one: the bill of materials (BOM)
Each product is made of components (materials or semi-finished goods), and each component can have its own tree. For each component you normally need two quantities: the gross quantity (what is consumed, including waste) and the net quantity (what stays in the product). The difference is the waste, which makes material planning more realistic. If your BOM is still in Excel, BOM in Excel or software? shows which columns a complete tree needs and when migration pays off.
Step two: material shortage calculation
The question is simple: "To make 500 units of this product, how much of each material do we need and how much are we short?" The software expands the tree, calculates total consumption of each component, compares it with warehouse stock and shows the shortage. The result can be saved for planning. This is the idea behind MRP, explained with an example in What is MRP?.
A simple example: for 500 units, if each unit uses 2 metres of profile, total consumption is 1,000 metres. If stock is 600 metres, the shortage is 400 metres and must be bought before production starts.
Step three: order analysis
In many factories production starts from a quotation or customer order. Order analysis splits each order into three supply groups: finished product, semi-finished goods and raw materials. From the same screen you can raise the next action for each group:
- for products and semi-finished goods: a production request or a temporary issue;
- for raw materials: a purchase order;
- for goods already in stock: a reservation, so they are not consumed by another order.
This is where a manufacturing ERP connects to the warehouse and purchasing. If order analysis lives in a separate file, reservations and requests are retyped and discrepancies appear.
Step four: planning by machine, shift and personnel
Once you know what to make, you need to know where and when. Planning at this stage includes:
- choosing the machine and the workshop or station;
- a start and end period, quantity and shifts (at least one shift);
- the station's personnel;
- overlap control, so one machine is not booked for two plans in the same period;
- a quantity check against "total quantity", "planned" and "remaining".
For batch production such as chemicals, batch planning also exists: production suggestion, product production plan and semi-finished processing. Planning by machine works, but note that the Gantt chart is not yet available in the web version and only shows a message. If a Gantt view is a requirement, clarify that point before buying.
Step five: recording personnel output and scrap
A plan is useless until it is compared with reality. The daily output document records who worked on which machine, in which shift, with what start and end time, and how much good output, scrap and rework was produced. Stoppages are recorded with a reason and start and end times. These data are the basis for production and capacity reports and show where scrap and stoppages really come from.
Step six: minimum, maximum and reorder point
A factory that buys materials in a panic every week usually has no minimum and maximum stock defined. For each item you can define a minimum daily production, average daily consumption, safety stock (in days), a reorder point and a critical point, so purchasing alerts are seen on time.
An example order flow
- A customer places an order and a quotation is recorded.
- Order analysis shows two semi-finished items are in stock and one material is short.
- A purchase order is raised for the short material and temporary issues (reservations) for stock on hand.
- Production is planned on a suitable machine and shift.
- At the end of the day output is recorded with good quantity and scrap.
- Reports show how far the plan was from reality.
A checklist for evaluating a manufacturing ERP
- Does it support a multi-level tree with gross and net quantities?
- Does it calculate shortages for any run size against warehouse stock?
- Can you raise a production request, temporary issue and purchase order directly from an order?
- Does planning control machine overlap?
- Are good output, scrap and rework recorded?
- Can minimum, maximum and reorder points be defined?
- Is production on the same database as the warehouse and accounting?
To see these steps on one page, see Afrandeh MRP and production. If quality control and machinery maintenance also matter, look at quality control and maintenance, and see Afrandeh ERP for the overall picture. If you want to see your own production process in Afrandeh, request a demo.
Frequently asked questions
How does a manufacturing ERP differ from a general ERP?
Besides purchasing, sales, warehouse and accounting, it adds a BOM, material shortage calculation, production planning and output recording, all on one database.
Is a Gantt chart available in the Afrandeh web version?
No, the Gantt chart has not yet been moved to the web version; planning by machine, shift and personnel works with overlap control.
How is the material shortage calculated?
For the chosen run size the product tree is expanded, total consumption of each component is compared with warehouse stock and the shortage is shown.