What Is MRP? Material Requirements Planning Explained with an Example

What MRP is, how gross and net requirements differ, how make-or-buy decisions are made and which mistakes break an MRP run.

By Afrandeh team3 min read

A new order has arrived and must ship in three weeks. Now the production planner needs to know: what materials does this order need, how much is in stock, how much has to be bought and what do we have to make ourselves? If the answers come from several Excel files and a few phone calls, material shortages usually show up on production day. MRP is the structured answer to exactly these questions.

What is MRP?

MRP stands for Material Requirements Planning. It starts from three inputs and produces one output:

  • Demand: which product, how much and by what date.
  • Product structure (BOM): which components and semi-finished items each product is made of.
  • Stock and incoming supply: how much is in the warehouse and how much is already being made or bought.

The output is the planned order: for each item, how much has to be made or bought and when to start.

Gross and net requirements

The key idea in MRP is the difference between the two. The gross requirement is the total that demand and the BOM call for. The net requirement is what actually has to be supplied:

Net requirement = gross requirement − warehouse stock − quarantined material − open work orders − incoming purchases

Example: if an order needs 500 metal frames, 180 are in stock, 20 are in quarantine because of a quality issue and 100 are on an open work order, the net requirement is 200. The subtle part is those 20 in quarantine: if they are not deducted, the planner believes they have material that cannot actually be used.

MRP works level by level

A BOM is usually multi-level: products are made of semi-finished items, and those are made of raw materials. MRP explodes the tree level by level; the net requirement of one level becomes the gross requirement of the level below. That is why an incomplete or outdated BOM breaks the whole calculation.

Three decisions MRP has to make

  1. Make or buy: an item with a valid BOM is made; everything else is bought.
  2. How much: the order quantity is usually rounded up to the item's order multiple.
  3. When: the start date is the need date minus the lead time. If that date has already passed, the item is late.

Common mistakes when running MRP

  • Unversioned BOMs: today's BOM change silently rewrites yesterday's plan.
  • Unrealistic stock: suspect or reserved material still counts as available.
  • Missing lead times: without a lead time, the order start date means nothing.
  • A gap between proposal and document: the planned order has to be re-entered by hand in another system.

MRP in Afrandeh

In Afrandeh MRP and production planning, demand comes from open sales quotations within a time horizon (90 days by default), and the released BOM is exploded level by level. Warehouse stock, quality-control quarantine, open work orders and incoming purchase requests are deducted from the requirement. Alerts such as late items, circular BOMs, missing released BOMs and missing lead times are shown separately. Each "make" row becomes a draft work order and the "buy" rows a purchase request, and once created, that quantity is not proposed again.

To see the same calculation on your own data, request a demo.

Tags:ProductionERP

Frequently asked questions

What is MRP?

MRP (material requirements planning) starts from demand, the product structure (BOM) and stock, and works out for each item how much has to be made or bought and when to start.

How is the net requirement calculated?

Net requirement equals the gross requirement minus warehouse stock, quarantined material, open work orders and incoming purchases.

Where does Afrandeh's MRP get its demand from?

From open sales quotations within a time horizon that defaults to 90 days. Sales forecasts are not yet supported as a demand source.