Quality control

What Is an NCMR? Nonconforming Material Reports from Discovery to Disposition and Corrective Action

What a nonconforming material report (NCMR) is, how disposition, MRB approval and CAPA work, and how to manage them in software instead of spreadsheets.

By Afrandeh team5 min read

You inspect an incoming shipment of raw material and find that part of it does not meet specification. Now several questions come up: what do we do with that quantity? Use it, send it back or scrap it? Who is allowed to decide? Until it is decided, does the material count as "in stock" or not? And how do we stop it happening again?

An organized answer to those questions is what quality control calls an NCMR.

What is an NCMR?

NCMR stands for Nonconforming Material Report. It is a formal record for material that does not meet specification, stating which item, how much, where it was found, what was decided about it and what was done to prevent a repeat. Many organizations use NCR (nonconformance report) and NCMR almost interchangeably; an NCMR focuses specifically on materials and goods.

Why a paper form or an Excel file is not enough

  • No formal number. When two people talk about "that nonconformance", it is not clear they mean the same one.
  • Decisions and quantities drift apart. Of 100 nonconforming units, how many were used, returned or scrapped? In Excel the parts rarely add up to the original quantity.
  • Approval of sensitive decisions is not recorded. Who allowed material with a deviation to be used?
  • Warehouse and planning are not told. Suspect material still counts as stock and the planner decides based on it.
  • Cost stays invisible. No one knows which item or supplier causes the most cost of poor quality.

The life of an NCMR in seven steps

  1. Discovery: the defect is found at incoming inspection, in process, at final inspection or from a customer return or complaint. Recording the source makes reporting possible later.
  2. Recording: a record opens with a title, discovery date, item, nonconforming quantity and severity (minor, major or critical) and gets a formal number such as NCMR-1405-0001.
  3. Root cause: the root cause is investigated with methods such as 5 Whys or an Ishikawa diagram and recorded.
  4. Disposition: the nonconforming quantity is split across one or more decisions.
  5. MRB approval: sensitive decisions must be approved by someone else.
  6. Execution and settlement: scrap and returns are completed with a warehouse document, rework and repair with a work order, and the quantity is released from quarantine.
  7. Corrective and preventive action (CAPA) and closure: the record does not close until the root cause is fixed.

Five possible dispositions

Disposition Meaning Note
Use as is The quantity is accepted and used despite the deviation. Because it departs from specification, it usually needs MRB approval.
Rework The item is reprocessed to bring it back to specification. The rework cost should be recorded.
Repair The item is repaired but may not fully meet the original specification. Needs approval, like "use as is".
Return to supplier The quantity is sent back to the supplier. Supports supplier evaluation.
Scrap The quantity is discarded or destroyed. The scrap value is part of the cost of poor quality.

One quantity does not have to get a single decision. Of 100 nonconforming units, 70 might be used as is, 20 reworked and 10 scrapped. The software should check that the parts never exceed the nonconforming quantity.

The MRB and separation of duties

The MRB (Material Review Board) reviews sensitive decisions about nonconforming material. A common rule is that "use as is" and "repair" always need approval, as does any decision on a "critical" NCMR. The more important principle is separation of duties: the person who records a decision should not approve it, and an approved decision should not be bypassed by deleting and re-entering it.

Quarantine: where quality meets planning

A frequent problem is that suspect material keeps counting as stock until it is dispositioned. The result: the production or purchasing planner assumes the quantity is usable and does not place the order needed, and on production day the material is not there.

The right approach is to separate the "nonconforming, not yet settled" quantity as quarantine and deduct it from usable stock in material requirements planning (MRP). Each quantity leaves quarantine only when its decision is actually carried out: scrap and returns when the warehouse document is issued, rework and repair when the work order closes, and use as is after approval.

Reporting: which item, which supplier?

Once every NCMR is in one system, you can report the number and quantity of nonconforming material and the cost of each decision by item, supplier and source of discovery. The same report answers questions such as "which supplier has the most returns?" or "are most defects found at incoming inspection or in process?" and feeds the cost of poor quality (COPQ).

CAPA: closing the loop

Dispositioning the quantity is only half the job. Corrective action (fixing the cause of this case) and preventive action (stopping a repeat) should be recorded with an owner and a deadline and go through "completed" and "verified" steps. Good practice is to close an NCMR only when all its actions are verified.

Checklist for setting up NCMRs

  • Define the sources of discovery and the severity levels.
  • Name the MRB members and the approval rule.
  • For each of the five dispositions, decide which document or order proves settlement.
  • Require an owner and a deadline for corrective action on every record.
  • Review a monthly nonconformance report by item, supplier and source.
  • Record rework and scrap cost so the cost of poor quality is visible.

NCMRs in Afrandeh

In Afrandeh quality control, every nonconformance is an NCMR with a formal number (such as NCMR-1405-0001) that can be linked to a batch inspection record or recorded on its own. In the same record:

  • the source of discovery, severity, root cause (5 Whys or Ishikawa) and a link to a customer complaint ticket are recorded;
  • the nonconforming quantity is split across the five dispositions, with a cost for each part;
  • sensitive decisions stay "pending" until an MRB member approves them, and the person who recorded them cannot approve them;
  • the unsettled quantity is deducted from stock as quarantine in Afrandeh MRP;
  • a warehouse document (for scrap and returns) or a work order (for rework and repair) is linked to the row;
  • an NCMR report by item, supplier and source of discovery is available;
  • corrective and preventive actions are recorded with an owner and a deadline, and once all are verified the NCMR closes automatically;
  • photos and documents can be attached and the NCMR report is printed with the system's print engine.

To see this cycle on your own data, request a demo.

Tags:Quality controlProductionERP

Frequently asked questions

What is the difference between an NCR and an NCMR?

An NCR is a nonconformance report in general and can cover a process or a document; an NCMR is specifically for nonconforming material and goods. In practice many organizations use both terms for the same record.

What does MRB mean?

MRB stands for Material Review Board: the members who approve or reject sensitive decisions about nonconforming material, such as using it with a deviation.

What does "use as is" mean?

Use as is means accepting a nonconforming quantity despite its deviation from specification; because it carries risk, it usually needs formal approval.

How long does quarantined material stay out of stock?

Until its decision is approved and carried out, for example when the scrap warehouse document is issued or the rework order is closed.

Are NCMRs only for raw materials?

No. A nonconformance can be found at incoming inspection, in process, at final inspection or from a customer return.